How to Break Up and Remove a Concrete Slab

Work out the weight before anything else. Concrete weighs about 2.4 tonnes per cubic metre, so a 20m² slab at 100mm is 4.8 tonnes — roughly a hundred wheelbarrow loads.

That figure decides the tools, the skip, the number of people and whether this is a weekend job or a contractor’s.

Working out the weight

Slab Volume Weight Barrow loads
3 × 2m at 100mm 0.6m³ 1.4 t ~30
4 × 3m at 100mm 1.2m³ 2.9 t ~60
5 × 4m at 100mm 2.0m³ 4.8 t ~100
6 × 3m at 150mm 2.7m³ 6.5 t ~135
Single garage, 150mm 2.6m³ 6.3 t ~130
Double driveway 40m², 150mm 6.0m³ 14.4 t ~300

Broken concrete occupies about 1.5 times the volume of the intact slab because of the voids between pieces. The weight is unchanged, but the skip fills faster than the calculation suggests.

Get your figure from the concrete weight calculator before booking anything.

Tools

Tool Suits Hire cost/day
Sledgehammer, 14 lb Under 50mm, small areas Buy, £35
SDS-max breaker Up to 100mm, domestic £30–£45
Electric breaker, 15–30 kg 100–200mm £45–£65
Petrol breaker Anywhere without power £55–£80
Floor saw / disc cutter Cutting to a clean line £50–£75
Mini digger with breaker Over about 25m² £180–£280
Bolt croppers Cutting mesh Buy, £30

The honest guidance: a sledgehammer is only realistic for a thin, unreinforced slab of a few square metres. Anything larger and you will hire a breaker on day two having achieved very little on day one.

Over about 25m², a mini digger with a hydraulic breaker attachment turns a week into a day. At £250 including delivery, it is usually cheaper than the hire, the skips and the time.

Breaking sequence: edges first

Concrete breaks by cracking away from a free edge. Attacking the middle of an intact slab just bounces the tool.

Work like this:

  1. Expose an edge by digging away soil or paving alongside it
  2. Break a strip 300 to 500mm wide along that edge
  3. Clear the debris so you have a genuine free face
  4. Work back across the slab in strips, always breaking towards the void
  5. Keep pieces to a size you can lift — roughly 300mm across for a 100mm slab

Where a slab is large or reinforced, saw-cutting it into sections first is worth the hire. Cut it into rough metre squares, then break each square — far faster than fighting a continuous slab, and the cuts give you free edges everywhere.

Undermining helps too. Digging out the sub-base beneath an edge removes the support, and the concrete then breaks with much less effort.

Mesh and rebar

Reinforcement turns broken concrete into a stubborn mat that will not lift.

Break the concrete first and expose the steel, then cut it with bolt croppers or an angle grinder as you go. Cutting into manageable sections as you work is far easier than freeing a whole slab and then trying to deal with the steel.

Wear gloves and eye protection. Cut mesh ends spring back and they are sharp.

Separate the steel from the rubble if you can. Scrap metal is worth a little, and hardcore skips are cheaper than mixed-waste skips.

What is underneath

Before the first blow, establish what the slab is sitting on and what runs through it.

Gas and water services are routinely laid under driveways and beside garages. Electricity supply cables often cross a drive to a garage or an outbuilding. Foul and surface water drains run under patios more often than not.

Check for inspection chambers, gullies, meter boxes and stopcocks in and around the slab, and follow the line they imply. Where a garage has power, assume a cable runs to it and find out which way.

A CAT scanner hires for around £30 a day and finds buried cables and metallic pipes. Plastic water pipe will not show, which is another reason to dig the first trench by hand rather than trusting a machine.

Also work out what the slab bears on. A slab poured over an old cellar, a filled-in pond or a soakaway needs different handling, and finding out with a digger track is not the way.

Moving the rubble

Load broken concrete into the barrow in a single layer along the bottom rather than heaping it. A heaped barrow of concrete is over 100 kg and will tip or break your back.

Lay scaffold boards for the barrow run. Pushing a loaded barrow across a lawn ruins the lawn and doubles the effort.

Two people alternating — one breaking, one clearing — is far more than twice as fast as one person doing both.

Removing only part of a slab

Cutting out a section and leaving the rest is common — a new doorway, a service trench, a failed patch.

Saw-cut the boundary first, full depth if you can. A disc cutter typically reaches 100mm, so on a thicker slab cut from both faces where accessible, or cut as deep as possible and accept a ragged break below the cut line.

Never break to an uncut line. The crack runs where it wants and takes a chunk of the slab you were keeping with it.

Then break inward from the middle of the cut-out towards the saw line, so the retained slab is never the free edge being levered against.

Where new concrete will meet the old, the cut face is your joint. Keep it square and clean, and drill in dowels if the two sections need to share load.

Realistic timescales

Slab By hand Breaker Digger + breaker
6m², 75mm 1 day 3 hrs —
12m², 100mm 3 days 1 day 2 hrs
25m², 100mm Impractical 2–3 days 4 hrs
40m², 150mm reinforced Impractical 5 days 1 day

These are breaking times only. Loading and removal typically doubles them.

Silica dust and safety

Cutting or breaking concrete releases respirable crystalline silica. Long-term exposure causes silicosis and lung cancer, and it is the reason dust suppression is a legal requirement on commercial sites rather than a suggestion.

The minimum:

  • FFP3 mask, fitted properly against clean-shaven skin. A cloth mask or FFP1 does nothing useful here.
  • Water suppression when saw-cutting — cutting dry indoors is genuinely dangerous
  • Eye protection, since flying fragments are the immediate risk
  • Ear defenders — a breaker runs at 100 dB or more
  • Anti-vibration gloves and regular breaks, as hand-arm vibration syndrome is permanent
  • Steel toe boots

Check for buried services before starting. Gas, water, electricity and drainage all get run under and beside slabs, and a cable plan or a CAT scanner is cheaper than the alternative.

On any building predating 2000, consider whether asbestos could be present in adjacent material — old garage floors sometimes sit alongside asbestos cement sheeting, and that needs a licensed contractor.

Common questions

How much does a concrete slab weigh?

About 2.4 tonnes per cubic metre. A 20m² slab at 100mm is 4.8 tonnes; a single garage floor at 150mm is around 6.3 tonnes.

What is the easiest way to break up concrete?

Work from an exposed edge inwards, never from the middle. Saw-cut large slabs into sections first, and undermine the edge so the concrete has nothing supporting it.

Do I need a digger to remove a slab?

Over about 25m², yes — a mini digger with a breaker attachment turns days into hours and usually costs less than the extra hire and labour.

Is breaking concrete dangerous?

The main risks are silica dust, noise and hand-arm vibration. An FFP3 mask, water suppression when cutting, ear defenders and regular breaks address all three.

How long does it take to break up a driveway?

A 40m² reinforced driveway is about five days with a handheld breaker, or one day with a mini digger — plus the same again for loading and removal.