A poured wall is a tall, thin pour, which makes it unforgiving. Get the volume wrong and you are left with a cold joint running horizontally through the wall at exactly the height the concrete ran out. Enter length, height and thickness below.
The formula
Volume = Length × Height × Thickness
Worked example. A retaining wall 6 m long, 1.2 m high and 200 mm thick: 6 × 1.2 × 0.2 = 1.44 m³. With 5% waste that is 1.51 m³, roughly 3.6 tonnes. Footings underneath are a separate pour — size them with the footing calculator and order both together.
Useful shorthand: a wall 1 m high and 200 mm thick swallows 0.2 m³ per linear metre. In imperial, a 1 ft high × 8 in thick wall takes 0.67 ft³ per linear foot.
Typical wall thicknesses
| Wall type | Thickness |
|---|---|
| Low garden retaining wall | 150–200 mm (6–8 in) |
| Basement or foundation wall | 200–300 mm (8–12 in) |
| Structural shear wall | Engineer’s design |
| ICF wall core | 150–200 mm (6–8 in) |
Any retaining wall over about a metre, and anything structural, needs designing properly. The load is not just soil weight — it is soil weight plus whatever water is trapped behind it.
Pouring a wall without ruining it
- Pour in lifts of about 500 mm, working around the wall rather than filling one end first. Vibrate or rod each lift to drive out trapped air, and keep going — do not stop for lunch halfway up.
- Brace the formwork harder than feels necessary. Wet concrete exerts real hydraulic pressure, and a blowout at 1.5 m is a very bad afternoon.
- Drain retaining walls. Weep holes at the base, free-draining gravel behind, and a perforated pipe to somewhere useful. Most retaining wall failures are water pressure failures, not concrete failures.
Frequently asked questions
How much concrete is in a wall per metre?
A wall 1 m high and 200 mm thick contains 0.2 m³ per linear metre. Scale it directly: double the thickness and you double the volume.
What grade for a retaining wall?
C25 to C30 for garden walls, C30 to C35 with reinforcement for engineered walls. Air-entrained if the wall faces freeze-thaw cycles.
When can I strip the formwork?
Vertical side shutters after 24 to 48 hours in warm weather, longer when it is cold. Anything propping a suspended element stays much longer. Design strength arrives at 28 days.
Should a poured wall be reinforced?
Retaining and structural walls, yes — vertical bars tied into the footing plus horizontal bars, to design. A low freestanding garden wall on a good footing may not need it.
Related calculators
- Concrete Slab CalculatorSlabs, pads, floors & shed bases
- Concrete Footing CalculatorStrip & pad footings, foundations
- Concrete Column CalculatorColumns, sonotubes & piers
- Concrete Stairs CalculatorSteps & staircases
- Curb & Gutter CalculatorCurbs, gutters & edging
- Concrete Bag CalculatorHow many bags do you need?
- Concrete Cost CalculatorReady-mix & bagged prices
- Mix Ratio CalculatorCement, sand & aggregate quantities
- Concrete Weight CalculatorWeight per m³, yard & cubic foot
- Ballast CalculatorBallast & cement for concrete (UK)
- Sand & Cement CalculatorMortar for patios & bricklaying
- Concrete Block CalculatorBlocks, bricks & mortar for walls
- Post Hole CalculatorFence posts & postcrete