Skip to content

How to Measure an Irregular Area for Concrete

Split the area into rectangles, triangles and part-circles, work out each one separately, and add them together. Every awkward shape yields to that method, and it needs nothing beyond a tape measure and a sketch.

The mistakes that cost money are almost never in the arithmetic. They are in the measuring — a dimension taken from the wrong point, a slope ignored, a cut-out forgotten.

Splitting into rectangles

Draw the shape roughly to scale on paper. Then divide it with straight lines into the fewest rectangles that cover it completely.

An L-shaped patio splits into two rectangles. A T-shape splits into two or three. A stepped edge splits into as many as it has steps.

Number each piece on the sketch and measure its length and width on site, writing the figures straight onto the drawing. Do not carry numbers in your head between the garden and the kitchen table.

The one rule: pieces must not overlap. Where you have drawn a dividing line, one rectangle stops and the next begins — count the shared strip once.

Triangles, circles and segments

Not everything is rectangular. Three more formulas cover almost all of the rest.

Shape Area Example
Rectangle length × width 4 × 3 = 12m²
Triangle ½ × base × height ½ × 4 × 3 = 6m²
Circle 3.14 × radius² 3.14 × 1.5² = 7.07m²
Half circle 1.57 × radius² 1.57 × 1.5² = 3.53m²
Quarter circle 0.785 × radius² 0.785 × 1.5² = 1.77m²
Ring 3.14 × (outer² − inner²) 3.14 × (2² − 1²) = 9.42m²
Trapezium ½ × (a + b) × height ½ × (5 + 3) × 4 = 16m²

For a triangle, “height” means the perpendicular distance from the base to the opposite corner, not the length of a sloping side. Measure it at right angles to the base.

The trapezium formula is worth remembering. A great many gardens are rectangles with one edge running out of square, and a trapezium handles that in one calculation instead of a rectangle plus a triangle.

Worked example: an L-shaped patio

A patio wraps around a corner of the house. The long leg is 6.0m × 3.0m. The short leg extends 2.5m further out and is 3.5m wide.

  • Rectangle A: 6.0 × 3.0 = 18.0m²
  • Rectangle B: 2.5 × 3.5 = 8.75m²
  • Total area: 26.75m²

At 100mm thick: 26.75 × 0.1 = 2.675m³. Add 10% for wastage and over-dig, and order 3.0m³.

Note what happened at the corner. Rectangle A was measured full length, so rectangle B starts where A stops — 2.5m, not the full 5.5m from the wall. Getting that wrong would have added 10.5m² and nearly a cubic metre of concrete.

Curved edges: the strip method

For a genuinely curved boundary that no formula fits, use strips.

Run a baseline — a taut string line along the straight side. Mark it at regular intervals, say every 500mm. At each mark, measure at right angles from the string to the curved edge.

You now have a series of depths. Average them, multiply by the length of the baseline, and you have the area to a very good approximation.

An example: a baseline 5m long, marked every 500mm, giving eleven measurements of 2.0, 2.2, 2.4, 2.5, 2.6, 2.6, 2.5, 2.3, 2.1, 1.8 and 1.5m. The average is 2.23m, so the area is 5 × 2.23 = 11.15m².

Closer intervals give better accuracy. On a tight curve use 250mm.

Sloping ground and average depth

A slab on ground that falls has a varying thickness, and using the shallow end will leave you short.

Set up a level line — a laser or a string line with a spirit level — and measure down to the ground at both ends and in the middle. The average of those readings is your average depth, and area × average depth gives the volume.

For a slab 5m long that is 100mm deep at the top and 220mm at the bottom, the average is 160mm. On a 15m² slab that is 2.4m³ rather than the 1.5m³ you would get from the shallow end. The difference is a whole extra part-load.

Measure the middle as well as the ends. Ground rarely falls in a straight line, and a dished middle adds volume that two end readings miss entirely.

Cut-outs and subtractions

Manholes, tree pits, drainage gullies and existing structures all reduce the area. Measure each and subtract.

Be realistic about small ones. A 600 × 600mm manhole is 0.36m² — on a 30m² slab that is barely 1%, comfortably inside your wastage allowance, and subtracting it just risks arithmetic error. Subtract cut-outs over about 1m²; ignore the rest.

Recording measurements so you can check them

Write everything on the sketch, on site, as you measure. Not on your phone, not on a loose scrap.

Record every dimension, even ones you think you can derive. Two measurements that should add up to a third give you a built-in check — if they do not, you know before ordering rather than after.

Measure diagonals on anything you believe is rectangular. Equal diagonals mean square; unequal means you have a trapezium and should treat it as one.

Date the sketch and photograph it. A month later, when the supplier asks a question, the photo answers it.

Volume at a glance

Once you have a total area, the volume follows from the depth. This table saves a calculation:

Area 75mm 100mm 150mm 200mm
5m² 0.38m³ 0.50m³ 0.75m³ 1.00m³
10m² 0.75m³ 1.00m³ 1.50m³ 2.00m³
15m² 1.13m³ 1.50m³ 2.25m³ 3.00m³
20m² 1.50m³ 2.00m³ 3.00m³ 4.00m³
30m² 2.25m³ 3.00m³ 4.50m³ 6.00m³
50m² 3.75m³ 5.00m³ 7.50m³ 10.00m³

These are finished volumes before wastage. Add 10% on top for a slab and 15% for anything excavated.

Adding it up without errors

The single most useful habit is to calculate the total twice by different routes.

Split the shape one way, add it up, then split it a different way and add it up again. If the two totals agree, you have it right. If they differ by more than a rounding error, one of the splits is wrong and you have caught it for free.

A second sanity check: pace the area out, or estimate it as a single rectangle that roughly encloses the shape. If your careful calculation says 26.75m² and the enclosing rectangle is 33m², that is plausible. If your calculation says 47m², something is wrong.

Feed the pieces into the slab calculator one at a time and add the volumes, or enter the total area with your average depth.

Common questions

How do I measure an irregular shape for concrete?

Split it into rectangles, triangles and part-circles on a sketch, measure each piece separately, and add the areas. Use the strip method for genuinely curved edges.

How do I calculate concrete for sloping ground?

Measure the depth from a level line at both ends and the middle, average those figures, and multiply by the area. Using the shallow end alone can leave you a third short.

Should I subtract manholes and cut-outs?

Subtract anything over about 1m². Smaller cut-outs fall inside your wastage allowance and subtracting them only adds a chance of arithmetic error.

How do I check my measurements are right?

Calculate the total twice by splitting the shape two different ways. If both routes agree you are right; if they differ, you have found an error before ordering.

What if my patio is not square?

Measure the diagonals. If they differ, treat the shape as a trapezium — half the sum of the two parallel sides, times the perpendicular width.

Work out your quantities